[INSERT Name of Project] Contractual Framework
Project Parameters
|
Formal Name of Project for Australian Govt:
(Also include formal name of building project if different) |
|
|
Type of project:
(e.g. Directly or Indirectly funded, Privately funded, Pre-commitment Lease) |
|
|
Total Project Value:
(as advised) |
|
|
Australian Government Funding Component
(if different from Total Project Value) |
|
|
Funding Entity:
(e.g. Department of Finance, Department of Defence) |
|
|
Funding Entity Contact Officer and Details
(name, position & section, telephone, email and postal address) |
|
|
Funding Recipient or Project Developer:
(for Indirectly Funded, Private or Pre-commitment lease projects only) |
|
|
Funding Recipient/Developer Contact and Details:
(name, position & section, telephone, email and postal address) |
|
|
Alliance Name:
(for Alliances, PPP and SPV projects only) |
|
|
Alliance Partners:
(for main parties and roles in forming the Alliance only) |
|
Deed & Tender details
|
Grant or Funding Deed date:
(e.g. date grant deed was signed/released from funding agent) |
|
|
Tender release date:
(e.g. dated tender was released to the public) |
|
|
Tender close date:
(e.g. dated tender was closed) |
|
|
Tender Number:
(e.g. tender number associated with tender) |
|
Contract and Construction Details
|
Contract name:
(e.g. the full contract name) |
|
|
Form of Head Contract:
(e.g. managing contract, lump sum, cost plus) |
|
|
Contract release/award date:
(e.g. date builder signed the contract) |
|
|
Construction start date:
(e.g. when first movements were made on site, surveying, breaking ground etc) |
|
|
Construction scheduled finish date:
(e.g. initial finish date plus any extra time for additions or changes) |
|
|
Construction Ahead or Behind Schedule:
(Number of weeks, Note 2 different schedules used) |
· Contract Schedule:
· Builders Schedule: |
|
Reason for delay/acceleration of Program:
(eg bad weather, fine weather, industrial issues) |
|
Attachments as applicable
(Ensure all DM permissions default to “read only” for CMG Secretariat)
|
Advertisement and/or AusTender Notice:
(should include any Code provisions) |
DM8 - |
|
Expression or Registration of Interest:
(should include general conditions and any Code provisions) |
DM8- |
|
Conditions of Tender:
(should include general conditions and any Code provisions) |
DM8- |
|
Head Construction Contract:
(should include general conditions and any Code provisions) |
DM8- |
|
Alliance Agreement (if applicable):
(should include all relevant conditions and any Code provisions) |
DM8- |
|
Undertakings of Code Compliance:
(from Head Contractor should be signed copy ) |
DM8- |
|
Undertakings - Future Privately Funded Projects: (if Undertakings are separate from above ) |
DM8- |
|
Head Contractors Workplace Arrangement:
(if possible signed and sealed copy ) |
DM8- |
|
Greenfields Agreement (if applicable):
(if possible signed and sealed copy ) |
DM8- |
|
DEEWR Assessment of Head Contractor:
(for Head Contractor and Greenfields) |
DM8- |
Head Contractor - Previous Code Contact with ABCC